Progress on the Construction of Samut Sakhon 1 High-Voltage Power Station in June-July 2016

“The construction of the GIS Control building is in midst of painting exterior structures and installing composite panels. The pump house building construction is in the process of welding the steel roof structure and laying walls. The SWG building had handrails and composite ceilings installed. Some ongoing outdoor works include cable trench installations, road works and drainage systems.”